Two quotes for a 100 t/day sunflower crushing line can differ by a factor of two and both be honest. The difference is rarely the press itself — it is where each supplier draws the boundary of the scope. This note sets out what actually moves the number, so you can compare offers on the same basis.
Capacity is a step function, not a slope
Crushing capacity does not scale smoothly. Between roughly 50 and 100 t/day you can build a compact or modular line with a small footprint. Between 200 and 500 t/day you are into a continuous line with silos, continuous conditioning, and a material handling system that costs more than the presses.
This is why a 200 t/day plant rarely costs twice a 100 t/day plant — it can cost two to three times as much, because the whole plant moves up a class: larger flaking rolls, continuous rather than batch conditioning, bigger meal handling, more steam.
| Seed input | Typical configuration | What changes in the budget |
|---|---|---|
| 50 – 100 t/day | Compact / modular | Presses dominate; civil and utilities are modest |
| 200 – 500 t/day | Continuous line | Material handling, continuous conditioning, steam capacity |
| 600 t/day and above | Continuous + extraction | Add solvent plant, meal despatch, larger utilities |
Prepress versus full press: where the money goes
A single full press on sunflower leaves 6–8% oil in the meal. Pre-pressing followed by solvent extraction takes that below 1%. The extraction plant adds capital, solvent handling, and a safety regime — but on any line above roughly 150 t/day the extra oil recovered usually pays for it.
Below that size the solvent plant often cannot be justified on oil alone, and the decision turns on whether you have an outlet for the meal and whether your site can carry the utilities.
The scope items that get left out
Budgets commonly quote the process equipment and skip: civil works and foundations, steam boiler and condensate, cooling tower or chiller, electrical distribution and MCC, compressed air, seed storage and finished oil tankage, laboratory, and freight and erection.
Ask every supplier for a scope boundary drawing — inlet to outlet, with everything outside listed separately. Two quotes can only be compared once both boundaries are drawn on the same diagram.
Automation and materials: the two dials you can turn
After the process route is fixed, cost is mostly set by two dials. Automation level — from local push-button panels to full PLC with historian — typically moves the electrical and instrumentation package by 15–30%. Material grade, especially stainless where the oil is hot or the meal is wet, moves fabrication cost noticeably.
Cutting these is legitimate, but cutting them after the layout is fixed is expensive. Decide them at the scope stage.
Questions buyers ask
How long does a 100 t/day sunflower crushing plant take to build?
Can used or refurbished equipment cut the budget?
Why do quotes for the same capacity differ so much?